Module 8: Operations, Projects & Implementation

8.4

Opportunity Framing

Define the problem, its cost and a measurable objective before you pick a solution.

Write down what is wrong (or possible), what it costs to leave it, and what success looks like in numbers, before anyone proposes a system, a hire or a project. The result is the page you hand to a decision maker, and the front end of 8.5 Project Charter Template.

Framing before solving is sound practitioner craft with no canonical original and little formal testing: practice, not research. The goal-setting research under the objective step is strong (Locke and Latham). The SMART acronym itself has no theoretical grounding, so it is used here only as a drafting check. Costs and targets are your own estimates unless sourced.

When to use it

Use it when:

Skip it when:

The idea

The habit this page installs is framing before solving. The logic is simple: a problem defined as a missing solution ("we need a new system") closes off every other answer and hides the outcome you actually want. The SMART part has a mixed pedigree. The acronym comes from a management magazine (Doran, 1981) and has little theoretical or empirical grounding of its own. What is strongly supported is the goal-setting research beneath it: specific goals tend to produce higher performance than vague ones, with documented side effects when goals are overweighted (Locke & Latham, 2002). Use SMART as a drafting discipline, not as a formula where ticking boxes guarantees a good objective.

So the problem statement and the do-nothing question come first and get the most time: if "what happens if we do nothing?" has no convincing answer, no polish will rescue the case. The objective asks for a baseline and a target, because a target without a baseline is a wish.

First step: State the Problem Without a Solution

Describe what is happening and to whom. If your sentence contains "implement", "buy" or "build", it is a solution.

Strong answer: "On Saturdays, visitors to the recycling center wait far longer than on weekdays, cars queue onto the public road, and staff report near-misses." Not: "We need a booking system."

Field Your answer
The problem or opportunity, in one or two sentences
Who is affected, and how
Cost of leaving it (money, time, risk, customers), with your estimate
What happens if we do nothing for a year?

Example

Illustrative example: the municipality, the roles and all figures are made up.

A municipal recycling center in Sweden hears the request "we need a booking system" after a busy summer. The center manager frames the problem first.

Section 1: "On Saturdays, visitors wait far longer than on weekdays, cars queue onto the public road, and staff report near-misses." Doing nothing for a year means more complaints and a safety risk the municipality owns.

Section 2: counted by staff on three Saturdays: about 35 minutes; weekday about 10. Target under 15.

Section 3: "Cut the average Saturday wait to under 15 minutes by the end of September. Owner: the center manager."

Section 4: out of scope: the two smaller sites and the road outside.

Section 5: hypothesis: arrivals bunch between 10 and 12 at one weighing station. Options: a booking system (high cost), a second lane (high cost), earlier opening plus peak-time signs (low cost). Recommended: try the cheap option for four Saturdays, measure, then decide.

Fill it in and keep your answers